MAJOR OVERHAULING OF SPM BUOY AT MUTHURAJAWELA

CPSTL planned to carryout major overhauling of the Single Point Mooring (SPM) buoy after 10 years of its installation in 2010 . This major task will take 45 days spending Rs. 500 million as per the plan. Overhauling work will be done at Colombo Dock yard under the supervision of Manufacturer M/s IMODCO. All other balance work (Removal and reinstallation of buoy) will be done by CPSTL employees saving huge cost to CPSTL. CPSTL and CPC have arranged fuel distribution of country without any interruption during this non operation period of SPM. Work is in-progress from 09th December 2020